5.14
Test and adjustment after repair, English
Test and adjustment after repair
AC leakage test
The product must be insulation tested after having been dismantled.
Follow the test procedure when the product has been reassembled and is ready to
be returned to the customer.

IMPORTANT

Flashover must not occur during the testing procedure!
Insulation test
Short-circuit the two pins of the mains plug and connect them to one of the terminals
of the insulation tester.
Connect the other terminal to ground on the aerial socket.
NOTE!
To avoid damaging the product it is essential that both terminals of the insulation
tester have good contact.
Test procedure
Slowly increase the insulation tester voltage until a voltage of 1.5kV and a maximum
current of 10 mA is obtained.
Maintain the voltage for 1 to 2 seconds, then slowly reduce it to 0V.