17. Cement as many sections and couplings of rigid 1" PVC pipe
needed to connect the 1" male PVC adapter in the discharge
tee to the 1" male adapter on the tank cross inlet. Set
pressure in the pre-charged pressure tank to
2 pounds less than the cut-in pressure of the pump. The
cut-in pressure of these pumps is factory preset to 30 PSI. If
this cut-in setting has not been changed, then the pre-
charged pressure tank should be set to 28 PSI. Total
installation should look like the shallow well drawing below.
18. To prime, remove plug from
the top of pump case. Fill
piping and pump with water
until the water overflows from
the top of pump case. Replace
plug and tighten to seal.
Install pressure gauge. Open
a faucet or two in the house.
Start motor. If pump is offset
from well 4 feet or more, it
may take a few minutes for
pump to prime. Failure to prime in 5 minutes: Stop
motor, remove pressure gauge plug from discharge
tee, add more water, try again.
123357
Shallow Well
123353 and 123355
Convertible
For parts or assistance, call Master Plumber Customer Service at 1-800-628-9439
WELL POINT PUMP INSTALLATION
Materials needed in addition to Shallow Well General
Materials, for Well Points only
• Enough galvanized 1-1/4" pipe and drive couplings to reach
from bottom of well to one foot above ground level
• One 1-1/4" galvanized elbow
• One 1-1/4" galvanized nipple
• One 1-1/4" check valve
• One 1-1/4" male PVC adapter
STEP 1: Drive the well point into the ground according to
the instructions included with your well point. Use as much
galvanized pipe and as many drive couplings as it takes to both
drive the well point 5-10 feet below the water table and leave
approximately one foot of pipe sticking out of the ground.
STEP 2: Thread 1-1/4" galvanized elbow onto the pipe sticking
out of the ground.
STEP 3: Thread 1-1/4" galvanized nipple into the 1-1/4" galvanized
elbow.
STEP 4: Thread 1-1/4" check valve onto the 1-1/4"
galvanized nipple.
STEP 5: Thread 1-1/4" male PVC adapter into the 1-1/4"
check valve.
STEP 6: FOLLOW STEPS 6–18 IN SHALLOW 4" DIAMETER CASED
WELL INSTRUCTIONS. Total installation should look like the
drawing below.
6116 1109
6
6117 1109

Publicidad

Tabla de contenido
loading

Este manual también es adecuado para:

123355123353

Tabla de contenido