Ingeteam
9. First connection to the electric grid
This chapter details the process for the charger's first connection to the grid.
First review the unit.
9.1. Unit inspection
You must check the correct condition of the installation before start-up.
Each installation is different, depending on its characteristics, the country in which it is located or other special
conditions which may apply. In all cases, before starting up, it is necessary to ensure that the installation complies
with the applicable legislation and regulations and that at least the part to be started up is complete.
9.1.1. Inspection
Before connecting the charger to the grid for the first time you must carry out a general inspection, which mainly
consists of:
Wiring inspection
•
Check that the cables are correctly joined to their connectors.
•
Check that these cables are in a good condition and that there are no hazards in their environment which
damage them, such as sources of intense heat, objects which could cut them or arrangements which put
them at risk of impacts or pulling.
Review the unit's fastening
Check that the unit is secured firmly and is not at risk of falling.
9.1.2. Hermetic sealing of the unit
Ensure during installation operations that the unit's level of sealing has not been altered during connection
operations.
Check the correct adjustment of the connectors and that any cable grommets are well sealed.
32
First connection to the electric grid
ABT2012IQM01_- Installation and Operation Manual