Flaring work

Main cause of gas leakage is defect in flaring
work. Carry out correct flaring work in the fol-
lowing procedure.
1
Cut the pipes
- Use the accessory piping kit or the pipes
purchased locally.
- Measure the distance between the
indoor and the outdoor unit.
- Cut the pipes a little longer than meas-
ured distance.
- Cut the cable 1.5m(4.9ft) longer than the
pipe length.
Copper
tube
90
2
Burrs removal
- Completely remove all burrs from the cut
cross section of pipe/tube.
- Put the end of the copper tube/pipe to
downward direction as you remove burrs
in order to avoid to let burrs drop in the
tubing.
Point down
3
Putting nut on
- Remove flare nuts attached to indoor and
outdoor units, than put them on
pipe/tube having completed burr removal.
(Not possible to put them on after flaring
work)
Slanted Uneven Rough
Pipe
Reamer
Flare nut
Copper tube
4
Flaring work
- Carry out flaring work using flaring tool as
shown below.
Bar
Bar
"A"
Copper pipe
Clamp handle
Outside diameter
mm
inch
Ø6.35
1/4
Ø9.52
3/8
Ø12.7
1/2
Ø15.88
5/8
Ø19.05
3/4
Firmly hold copper tube in a bar(or die) as
indicated dimension in the table above.
5
Check
- Compare the flared work with figure.
- If flare is noted to be defective, cut off
the flared section and do flaring work
again.
Smooth all round
Inside is shining without scratches.
Inclined
Even length
all round
13
Handle
Yoke
Cone
Red arrow mark
A
mm
inch
1.1~1.3
0.04~0.05
1.5~1.7
0.06~0.07
1.6~1.8
0.06~0.07
1.6~1.8
0.06~0.07
1.9~2.1
0.07~0.08
= Improper flaring =
Surface
Cracked Uneven
damaged
thickness