3.3.2 Installation of lifting platforms
When the lift is installed in the pit or on the floor with the groove of the platform turntable located in the front of the vehicle-entering
direction and the side slide plate of platform equipped with LED lights towards the inside, insert sizing blocks under the platform, lift the
lifting platform with a forklift or other lifting equipment (Fig. 5) to about 1,000mm height, so as to ensure that the mechanical safety device
is activated and locked.
- To avoid the failure of the mechanical safety device, a wood block can be inserted at the middle of the connecting
rod. When the hydraulic system is not fully filled with hydraulic oil and has the lifting and lowering actions, do not
work under the lift. Move the lifting platforms, adjust the distance between two platforms to make them parallel, and
connect the electric circuit, oil circuit and pneumatic circuit of two platforms as specified in the Wiring Diagram and
Oil Circuit Connection Diagram.
- Only after the hydraulic system connection is completed, the pneumatic circuit connection can be conducted.
- Oil pipes, electric wires and air pipes shall not be damaged.
- When inserting the oil pipes and air pipes into the pit from the control cabinet via PVC ducts, pay special attention to
the protection of pipe joints so as to prevent the damage to hydraulic system caused by foreign matter entering the
oil circuit and pneumatic circuit.
- Connection of electrical circuit: Connect the electrical circuit according to the wire diameter and wire size specified in
the Electrical Wiring Diagram.
AE5301S/AE5301-3S