6 Initial Setup and Start
1. Main screen. Current and daily yield.
This section contains:
Actual output power (kW)
Yield of the current day (kWh)
Total yield (kWh)
Current date and current time
Operating mode (#)
2. Inverter information. This section contains:
Device type and name of the inverter
Inverter serial number
IP Address
Serial number of the SMA Inverter Manager
Software version of the inverter
3. Actual values This section contains:
PV voltage and current
Phase-to-phase voltages
Phase currents
Grid frequency

6.2 Initial Setup via LCS-Tool

The inverter and the SMA inverter manager must be
commissioned via the local commissioning and
service tool (LCS-Tool). Commissioning is necessary
before the inverter starts feeding into the utility grid.
The LCS too enables the selection of predefned
country data sets for different utility grids.
Customer-specifc country data sets can be provided
by SMA and imported via the LCS-Tool (see
installation manual of the SMA Inverter Manager /
SMA Digital I/O Box / LCS-Tool).
34
SHP75-10-STP60-10-IA-xx-19
6.3 Switching on the DC
Load-Break Switch
Switch on the DC load-break switch at the inverter
and, if available, at the PV array junction box.

6.4 Commissioning

The inverter starts automatically if sufcient solar
irradiation is available. Starting takes a few minutes.
During this period, the inverter performs a self-test.
Observe the specifed sequence for commissioning
for the respective device type.
STP 60-10 with one-piece enclosure lid or SHP
75-10 with two-piece enclosure lid
1. Close the inverter ((see Section 5.12, page 31)).
2. Restore the DC power supply in the distribution
board (DC-Combiner).
3. Switch on the AC miniature circuit breaker of all
three line conductors.
4. Turn the DC load-break switch of the inverter to
position I.
STP 60-10 with two-piece enclosure lid
1. Close the inverter ((see Section 5.12, page 31)).
2. Turn the DC load-break switch of the inverter to
position I.
3. Restore the DC power supply in the distribution
board (DC-Combiner).
4. Switch on the AC miniature circuit breaker of all
three line conductors.
SMA Solar Technology AG
Installation Guide

Publicidad

Tabla de contenido

Solución de problemas

loading

Este manual también es adecuado para:

Sunny tripower 60Shp 75-10Stp 60-10

Tabla de contenido