To do this, first of all turn the safety lock placed
on the frontal lower right part (see drawing
D18) with an Allen wrench.
Extract the mobile part, tilt it upwards by the
frontal (see drawing D20) and pull back. In this
way, the components are separated. You must
foresee a support to leave the equipment at the
moment of the extraction.
Placing the frame
Once the installation is finished you will be able to assemble the frame. Please proceed as follows:
Take out the unit and place the frontal, fix it with the lateral screws on both sides of the unit taking care that the flanges
D20
of the frame remain outside (see drawing D20).
6
STARTUP
The ignition of this kind of equipments is automatic, so, please do not put on the burner any kind of material to ignition.
It is forbidden to use liquid substances such as alcohol, gasoline, petroleum or similar products. The use of this substance
leads the loss of warranty.
Before the ignition, follow the next verifications:
-
The electrical cable must be connected to the electrical network (230 Vac) with a socket equipped with earthing system.
-
The bipolar switch, placed on the rear side of the stove, must be in position I.
-
The pellet tank must be supplied.
-
The combustion chamber must be clean.
-
The burner must be clean and properly placed.
-
The combustion chamber door must be closed correctly.
During the first ignition could happen that the stove has finished the ignition cycle and there is no flame. In this case the stove automatically
starts an alarm state. This happens because the fuel feeder is empty and needs a moment to fill in. To solve this problem start again the stove
(taking into account the previous considerations) until the flame appears.
The stove or insert, at the beginning, must be subject to different start-up cycles so that all materials and the paint can complete different
elastic expansions.
At the beginning, it is possible that you note smoke or smell which are typically produced when metals are subject to high temperatures or
when the paint is still fresh. This paint is boiled at 80º C for a few minutes when construction, but it must exceed for a time the temperature of
200 ºC before the adhesion to the metallic surfaces.
Therefore, it is important to adopt these measures during the ignition phase:
1.
Assure that there is a good air refill in the place where the equipment is installed.
2.
During the firsts ignitions, keep a low power work and the oven lit during at least 6-10 hours continuously.
3.
Repeat this operation at least 4-5 times or more, depending on the needs.
4.
During the first ignitions, you should not place any object on the equipment and, in particular, on lacquered surfaces. Lacquered
surfaces should not be touched while the equipment is heated.
6.1
TUNING OF THE REMOTE CONTROL AND RECEIVER
Your equipment is provided with a remote control and a receiver. If both of them are not tuned the following message will appear l: "CERCA
CAMPO" (see drawing D21).
To tune them, follow the next steps:
-
You must turn off the general power supply switch of the equipment (drawing D21).
-
Press at the same time buttons number 1 and 2 of the remote control until the screen shows "SEGLI UNITA" (see drawing D22).
-
Select the radio frequency channel you prefer: 0, 1, 2 or 3.
-
Restart the general power supply switch of the equipment (drawing D23).
-
At the end, press red button number 3 of the remote control until both devices are connected.
-
When they are tuned the screen will show the original state (see drawing D24).
INSTALLATION, OPERATING AND SERVICING INSTRUCTIONS
D18
31
D19
RADIOFREQUENCY SERIES