2.1. Preliminary work
Unpack all the components of the station and check that there are no missing parts (for the content
of the supply, see section C) ; also check that they are in perfect condition.
Define an installation site so that the inlet and outlet pipes are as short as possible.
Remove the cover from the neutralization tank.
For the N-210 model, adapt the neutralisation granulate filling area to the performance of the
condensing boiler to be connected. To do so, assemble the plates as shown in figs. D-4 and D-5.
Insert the neutralisation granulate as shown in figs. D-2, D-3, D-4 and D-5.
As may be required, install the accessories as detailed in the user manual supplied.
______________________________________________________________________________________________________________________________________________________________________
00ANO0001-#
Fig. D-1: Assembly example
Fig. D-2: N-70 granulate filling height
-
- 23
Neutralisation Station
Neutra-N70 ; -N210
GB