LipuJet - P -RB / - RD / - RM / - RA / - RAP
Installation
2.14.2 Position
2.14.3 Assembly
The opening
bottom part: The opening is open and
the stud bolts [ 10 ] are mounted.
Push the socket seal [ 11 ] into the
opening as far as it will go (1).
The following parts are mounted
together as an assembly on delivery:
T-connector [ 15 ] , discharge socket
[ 16 ] , flange [ 13 ] and submersible
pipe [ 12 ]
Push the assembly through the opening
until the flange [ 13 ] touches the
bottom section. Drill flange holes over
the stud bolts [ 10 ] . Slide the washers
[ 14 ] over the stud bolts [ 10 ] . Screw the
nuts [ 14 ] onto the stud bolts [ 10 ] and
tighten them crosswise by hand (2).
92/ 454
The direct suction unit can be
positioned to the
of the centre axis of the tank.
Assembly on the left
below.
Heaviest single component or assembly approx. 15 kg.
Numbers in brackets " [ ] ",
"Components".
is pre-prepared in the
right
or left
described
Representation of the components _ Chap. 2.14.1
2.
1.