7.12 Initialisation run

The number of interconnected lifting columns is recorded during the initialisation run.
An initialisation run on the lifting columns must take place before installing the lifting
columns. The lifting columns should not be interconnected mechanically at this time.
Other connections and mechanical factors which may damage the lifting columns
must not be present. There is a danger of breakage.

7.12.1 When must you perform an initialisation run?

An initialisation run must always be performed if
a lifting column is going to be operated for the first time or
the number of interconnected control units has been changed or
the lifting column has been reset to the factory settings or
the lifting column prompts a run by means of E000 or
if an error is present (see error table, 7.18).

7.12.2 Performing an initialisation run

Any hand switch can perform the initialisation run.
Ensure that all lifting columns are interconnected and that the mains plug is not connected.
If you have pulled out the mains plug to perform an initialisation run, wait for at least 30 se-
conds before plugging it back in.
Keep the DOWN key
Plug the mains plug in and wait for about 5 seconds.
Note: The software release (e.g. "0217"), the lift column type connected (e.g. "-20-") and "[In
d]" appears in the hand switch display.
Release the DOWN key
Press the DOWN key
lower end position.
Note: When the lower end position is reached, "[In U]" appears in the display.
Press the UP key
position.
The initialisation run is complete. The lifting column is ready for operation.
Using the hand switch is described on 7.7.
An initialisation run must be fully completed because the lifting columns will not move otherwise.
This is equally true if no initialisation run has been performed.
If no initialisation run is to be performed, do not press the DOWN key in the first 5 seconds
after connecting the mains plug!
on the hand switch pressed.
.
again and keep it pressed until all lifting columns have moved to the
and keep it pressed until all lifting columns have moved to the upper end
7. Working life