7

Commissioning

7.1

Commissioning Procedure

This section describes the commissioning procedure and gives an overview of the steps you must
perform in the prescribed order.
Procedure
1.
Commission the inverter.
2.
Establish a connection to the user interface of the inverter.
There are various connection options to choose from for
this:
• Direct connection via WLAN
• Direct connection via Ethernet
• Connection via WLAN in the local network
• Connection via Ethernet in the local network
3.
Log into the user interface.
4.
Select the inverter configuration option. Please note that
the SMA Grid Guard code (a charge is levied for this
code) for changing the grid-relevant parameters must be
available after completion of the first ten feed-in hours or
installation assistant (see "Application for the
SMA Grid Guard code" available at www.SMA-So-
lar.com).
5.
Ensure that the country data set has been configured cor-
rectly.
6.
Make further inverter settings as needed.
7.2

Commissioning the Inverter

Requirements:
☐ The AC circuit breaker must be correctly rated and mounted.
☐ The inverter must be correctly mounted.
☐ All conductors must be correctly connected.
☐ Unused enclosure openings must be sealed tightly with sealing plugs.
Installation Manual
7 Commissioning
See
see section 7.2, page 49
see section 7.3, page 50
see section 7.4, page 55
see section 7.5, page 56
Inverter user manual
Inverter user manual
SBSxx-US-10-IA-xx-11
49

Publicidad

Tabla de contenido
loading

Tabla de contenido