5.1) Testing
Each component of the system, e.g. safety edges, photocells,
emergency stop, etc. requires a specific testing phase. We therefore
recommend observing the procedures shown in the relative instruc-
tion manuals. To test RUN, proceed as follows:
1. Ensure that the instructions outlined in this manual and in particu-
lar in chapter 1 "WARNINGS" have been observed in full;
2. Release the gearmotor as shown in "Release and manual move-
ment" paragraph in chapter "Instructions and Warnings for users
of the RUN gearmotor"
3. Make sure you can move the door manually both during opening
and closing with a force of max. 390N (40 kg approx.).
4. Lock the gearmotor.
5. Using the control or stop devices (key-operated selector switch,
control buttons or radio transmitter) test the opening, closing and
5.2) Commissioning
Commissioning can take place only after all the testing phases of the
RUN and the other devices have been completed successfully. It is
not permissible to execute partial commissioning or to enable use of
the system in makeshift conditions.
1. Prepare and store for at least 10 years the technical documenta-
tion for the automation, which must include at least the following:
assembly drawing of the automation, wiring diagram, analysis
of hazards and solutions adopted, manufacturer's declaration of
conformity of all the devices installed (for RUN use the annexed
CE declaration of conformity); copy of the instruction manual and
maintenance schedule of the automation.
2. Affix a dataplate on the gate providing at least the following data:
type of automation, name and address of manufacturer (person
responsible for the "commissioning"), serial number, year of
manufacture and "CE" marking.
6) Maintenance and Disposal
This charter provides information about how to draw up a maintenance schedule, and the disposal of RUN.
6.1) Maintenance
The automation must undergo maintenance work on a regular basis,
in order to guarantee prolonged lifetime; to this end RUN has a man-
oeuvre counter and maintenance warning system; see paragraph
"7.4.4 Maintenance warning".
!
The maintenance operations must be performed in strict
compliance with the safety directions provided in this manual
and according to the applicable legislation and standards.
If other devices are present, follow the directions provided in the cor-
responding maintenance schedule.
6.2) Disposal
As in the case of installation, at the end of the product lifetime, dis-
posal procedures must be carried out by qualified personnel
This product comprises various types of materials, some of which
can be recycled while others must be disposed of. Check informa-
tion on the recycling and disposal procedures according to local
legislation for this product category.
!
Some parts of the product may contain pollutant or haz-
ardous substances; if disposed of into the environment these
may constitute a serious risk of damage to the environment
and public health.
12
stopping of the gate and make sure that the leaves move in the
intended direction.
6. Ensure correct operation of all safety devices, one by one (photo-
cells, sensitive edges, emergency stop, etc.) and check that the
gate performs as it should. In particular, each time a device is
activated the "BlueBUS" LED on the control unit flashes 2 times
quickly, confirming that the control unit recognizes the event.
7. If the hazardous situations caused by the movement of the leaf
have been safeguarded by limiting the force of impact, the impact
force must be measured according to EN Standard 12445. If the
adjustment of the "obstacle detection sensitivity" and control of
the "motor torque" are used to assist the system for the reduction
of the impact force, try to find the adjustment to obtain optimal
results.
3. Post a permanent label or sign near the gate detailing the oper-
ations for the release and manual manoeuvre.
4. Prepare the declaration of conformity of the automation system
and deliver it to the owner.
5. Prepare the "Instructions and warnings for the use of the auto-
mation system" and deliver it to the owner.
6. Prepare the maintenance schedule of the automation system and
deliver it to the owner; this must provide all directions regarding
the maintenance of the single automation devices.
7. Before commissioning the automation system inform the owner in
writing regarding residual risks and hazards (e.g. in the "Instruc-
tions and warnings for the use of the automation system").
1. RUN requires scheduled maintenance work every 6 months or
20,000 manoeuvres (max.) after previous maintenance.
2. Disconnect all power supplies.
3. Check for any deterioration of the components which form the
automation, paying particular attention to erosion or oxidation
of the structural parts. Replace any parts which are below the
required standard.
4. Check the wear and tear on the moving parts: pinion, rack and
the leaf components; if necessary replace.
5. Connect the electric power sources up again, and carry out the
testing and checks stated in Paragraph "5.1 Testing".
As indicated by the symbol in figure 22 never
dispose of this product in domestic waste.
Apply classified waste collection procedures
for disposal in accordance with local regula-
tions or return the product to the retailer
when purchasing a new model.
Local regulations may envisage serious fines in the event of illegal
disposal of this product.
22