INSTALLATION
• Support Installation
1. Determine primary direction of prod-
uct flow. Figure 4A indicates the pre-
ferred flow as related to the drive.
2. Refer to "Match-Mark" numbers on
ends of conveyor sections. (Figure 4A)
Position them in this sequence near the
area of installation.
3. Attach supports to both ends of drive
section and to one end of intermediate
or tail sections (Figure 4A). Hand tighten
bolts only at this time.
4. Adjust elevation to required height.
• Ceiling Hanger Installation
If conveyors are to be used in an overhead application, ceiling hangers may
have been supplied in place of floor supports.
Figure 4B shows how a ceiling hanger mounts to a conveyor section. Ceiling
hangers should be mounted at section joints. For safety information concern-
ing conveyors mounted overhead, refer to "Installation Safety Precautions"
on Page 3.
NOTE: When installing ceiling hanger rods in an existing building,
all methods of attachment must comply with local building codes.
FIGURE 4B
MOUNTING BOLTS
(TORNILLOS DE MONTAJE)
SIDE CHANNEL
(CANAL LATERAL)
PIPE RETAINER
(ABRAZADERA)
LOCK BOLT
(TORNILLO CANDADO)
FIGURE 4D
AIR SUPPLY TO AIR VALVES
(SUMINISTRO DE AIRE A LAS VALVULAS DE AIRE)
MAIN AIR SUPPLY
(LINEA PRINCIPAL DE AIRE)
3/8" NPFT INLET
(ENTRADA NPFT DE 3/8")
FILTER/REGULATOR
(FILTRO/REGULADOR)
FIGURE 4A
FLOW
DRIVE SECTION
(SECCION MOTRIZ)
ADJUST TO DESIRED ELEVATION
(ADJUSTE A LA ELEVACION DESEADA)
NOTE: Elevation is determined as
Distance from Floor to Top of Rollers.
CEILING HANGER ROD
(VARILLA COLGANTE
AL TECHO)
SPACER
(ESPACIADOR)
JAM NUT
(CONTRA TUERCA)
SUPPORT PIPE
(TUBO DE SOPORTE)
JAM NUT
(CONTRA TUERCA)
FIGURE 4C
SIDE CHANNEL
(CANAL LATERAL)
FIGURE 4E
(CONTROLADOR DE ZONA DEL EZLOGIC®)
GAUGE
(MEDIDOR)
BOWL GUARD
(TAZON PROTECTOR)
INTERMEDIATE OR TAIL SECTION
(SECCION DE RETORNO O INTERMEDIA)
• Conveyor Set-Up
1. Mark a chalk line on floor to locate centerline of the conveyor.
2. Place the drive section in position.
3. Place remaining sections on extended support of previous section
(Figure 4A and 4C).
4. Insure that each bed sections is square prior to setting in place. Refer to
Figure 5. Page 5 for Instructions on How To Square The Beds. Bed sec-
tions must be square in order for the belt to track properly.
5. Fasten sections together with butt couplings and pivot plates (Figure 4C.
Hand tighten bolts only at this time.
6. Tighten all butt coupling and support mounting bolts and lag conveyor
to floor.
7. Connect air lines and cordsets at section joints as shown in Figure 4E.
8. Connect main air supply line to Filter/Regulator (Figure 4D).
CONVEYOR SET-UP CONT.
9. Connect 110 VAC power to power supply and connect 24 VDC power
from power supply to conveyor.
Component Manual for more information on power supply connections.
10. Set Regulator to working pressure of 35 P.S.I. NOTE: See Packing
Envelope for maintenance instructions on How to Adjust & Lubricate the
Filter/Regulator.
11. Install electrical controls and wire motor. See Page 6.
12. Track belt per instructions on Page 6 & 7.
MOUNTING BOLT
(TORNILLO DE MONTAJE)
EZLOGIC® ZONE CONTROLLER
3/8" AIR LINE
(LINEA DE AIRE)
4
"MATCH MA K NUMBERS"
R
(ETIQUETAS DE SECUENCIA DE ARMADO)
MARK D123456
MARK D123456
CONVEYOR F.O # 423568
CONVEYOR F.O # 423568
ITEM
1
TO
2
ITEM
2
HYTROL CONVEYOR CO., INC.
HYTROL CONVEYOR CO., INC.
JONESBORO, AR
JONESBORO, AR
NOTE:
See the EZLogic
SIDE CHANNEL
(CANAL LATERAL)
BUTT COUPLINGS
(ACOPLES DE
EXTREMO )
PIVOT PLATE
(PLACA PIVOTE)
STATIONARY SUPPORT
(SOPORTE ESTACIONARIO)
1/4" AIR LINE
CORDSET
(LINEA DE AIRE)
(CABLE)
AIR VALVE
(VÁLVULA DE AIRE)
TO
1
GEN 3
®