Screw Installation
42
42
Inside the building, beginning in each corner, secure rear
fascia gable with screws to back wall panels. Pre-drilled
holes should line up where the panels are joined. It is help-
ful to have one person on the outside of the building push-
ing down on the fascia gable while the second person inserts the screw
from the inside. Install 3 screws into both front fascia gables beside door
opening while one person holds the fascia gables down from the outside.
IMPORTANT: Be sure to check door alignment several times during
screw installation to ensure building has not moved out of alignment.
44
44
Inspect side
wall to ensure it
is visually
straight. Upon
confirmation,
install screws into the slope
wall caps working away from
centre.
43
43
slightly while the remaining screws are installed in the
lintel. While keeping upward pressure on the lintel install
screws to fasten fascia gables to front wall.
45
Finish by
45
installing a
screw at the
bottom of all
panels - front,
back and sides into base
channels on inside only
(Note: holes in exterior of
base channels are for
drainage only). DO NOT
INSTALL SCREWS IN THESE
DRAINAGE HOLES.
16
THE BALMORAL
Install the remaining screws in the lintel and
front fascia gables (#10 x 3/4" (1.9cm)).
Have one person push the lintel upward at
the centre so as the lintel bends upward
Mark hole locations on inside
46
46
of door while slide lock is held
into the hole provided in the
lintel. Drill 3 holes, 1/16" dia.
into the door (make sure that
the drill does not penetrate the exterior side of
the door). Install slide lock with #10 x 3/4"
(1.90cm) screws provided.