Problem
Possible causes
EEBus pairing was not successful or there was
a brief disconnection
The phase assignment of the EEBus device is
incorrect
A fuse has tripped that the energy manager
does not protect
The vehicle does not charge the
Current converters are connected the wrong
available surplus solar power
way around
Current converter not configured or config-
ured incorrectly
EEBus pairing was not successful or there was
a brief disconnection
The phase assignment of the EEBus device is
incorrect
Configuration of photovoltaic system incor-
rect
Remedial action
e
Repeat the EEBus pairing on the EEBus device and strengthen the commu-
nication signal (WiFi or PLC) if necessary.
g Follow the instructions for the EEBus device.
e
In the Web Application of the HOME INSTALLATION, check whether (the
correct) current transformers have been assigned to the electrical load.
e
Current converters to protect other fuses of lines in the direction of the
EEBus device can be purchased from your Porsche partner.
e
Have this installed and configured by an electrician.
e
Electrically skilled person checks whether the direction of arrow of the
current converter is pointing toward consumption and whether the cables
are connected correctly to the plug connectors J200, J300 and J301.
e
Check whether the connection positions of the current converters on the
energy manager match the configuration in the Web Application of the
HOME INSTALLATION (CT#). In addition, the configured phases of the
current converters must correspond to the phases of the voltage measure-
ment.
e
Repeat the EEBus pairing on the EEBus device and strengthen the commu-
nication signal (WiFi or PLC) if necessary.
g Follow the instructions for the EEBus device.
e
In Web Application of the the HOME INSTALLATION, check whether (the
correct) current converters have been assigned to the EEBus device or
whether there is a phase rotation when connecting the EEBus device. If
necessary, an electrician may change the configuration or the wiring.
e
An electrician checks whether the photovoltaic system is connected on the
mains side or the load side and checks the corresponding configuration
in the Web Application of the HOME INSTALLATIONas well as the assign-
ment of the phases and current transformers.