Commissioning

7.1

Commissioning Procedure

This section describes the commissioning procedure and gives an overview of the steps you must
perform in the prescribed order.
Procedure
1.
Commission the inverter.
2.
Establish a connection to the user interface of the inverter.
There are two connection options available to choose
from:
• Direct connection via WLAN
• Connection via Ethernet in the local network
3.
Log into the user interface.
4.
Select the inverter configuration option. Please note that
the personal SMA Grid Guard code for changing the
grid-relevant parameters must be available after comple-
tion of the first ten feed-in hours or installation assistant
(see "Application for the SMA Grid Guard code" avail-
able at www.SMA-Solar.com).
5.
If necessary, set the parameters for voltage and frequency
monitoring.
6.
Ensure that the country data set has been configured cor-
rectly.
7.
Make further inverter settings as needed.
7.2

Commissioning the Inverter

Requirements:
☐ A means of disconnecting the inverter from the PV array must be present.
☐ The AC circuit breaker must be correctly rated and mounted.
☐ The inverter must be correctly mounted.
☐ All cables must be correctly connected.
☐ Unused enclosure openings must be sealed tightly with sealing plugs.
Installation Manual
7 Commissioning
See
see section 7.2, page 41
see section 7.3, page 43
see section 7.4, page 45
see section 7.5, page 46
see section 7.6, page 48
Inverter user manual
Inverter user manual
STP50-US-40-IA-en_es-11
41

Publicidad

Capítulos

Tabla de contenido
loading

Tabla de contenido