4. INSTALLATION
1 - ASSEMBLY OF THE VERTICAL PUMP UNIT WITH ANGLE TRANSMISSION
- WITH OR WITHOUT BOOSTER -
The vertical pump unit consists of the following components:
– Command with angle transmission
– Axis line
– Pump body – Intake pipe (if any)
– Foot valve
WARNING!
All of these operations, including lifting and handling, must be performed in com-
pliance with the applicable safety regulations. Thoroughly clean all the parts that
come into contact with flanges/threads, ends of shafts, taking care not to touch the
rubber parts with oils, greases, solvents.
1.1 - ASSEMBLY OF INTAKE PIPE WITH FOOT VALVE
Before assembly, check the valve for smooth operation.
- Using suitable lifting equipment (crane or other), lift the intake pipe (T) complete with foot valve
(V) by means of a bracket (S) hooked under the pipe flange (F) (equipment provided by assembler).
(Fig.21)
- Lower the unit in the well, resting the flange on the support.