Tabla de contenido

Publicidad

Idiomas disponibles

Idiomas disponibles

SMA Solar Technology AG
3. Install the short circuit device.
4. Connect the measuring device for insulation resistance.
5. Short-circuit the first string.
6. Set the test voltage. The test voltage should be as close as possible to the maximum system
voltage of the PV modules but must not exceed it (see datasheet of the PV modules).
7. Measure the insulation resistance.
8. Eliminate the short circuit.
9. Measure the remaining strings in the same manner.
☑ If the insulation resistance of a string deviates considerably from the theoretically
calculated value, there is a ground fault present in that string.
10. Reconnect to the inverter only those strings from which the ground fault has been eliminated.
11. Reconnect all other strings to the inverter.
12. Recommission the inverter (see inverter installation manual).
13. If the inverter still displays an insulation error, contact the Service (see Section 9, page 62).
The PV modules might not be suitable for the inverter in the present quantity.
6.4
Resetting the Operation Inhibition after Detection of an
Arc Fault
If the red LED is glowing and the event number 4301 or 4302 is shown in the event list on the user
interface of the inverter, the inverter has detected an electric arc and interrupts feed-in operation.
Procedure:
1.
Danger to life due to electric shock
• Disconnect the inverter from any voltage sources (see the inverter installation manual).
2. Ensure that the PV modules, the connected DC cables and the terminal block for the DC
connection are not defective.
Repair or replace defective PV modules, DC cables or terminal block for the DC connection.
3. Recommission the inverter (see inverter installation manual).
4. Activate the user interface (see Section 4.1, page 19).
5. Log into the user interface as an Installer (see Section 4.2, page 23).
6. Reset the operation inhibition by setting one of the following parameters:
• Select the parameter Reset operating data and set to Reset operation inhibition.
or
• Select the parameter AFCI switched on and set to No and then back to Yes.
☑ This effects resetting of the operation inhibition and the inverter will start feeding in again.
User Manual
DANGER
STP33-62-US-41-BA-en_es-10
6 Troubleshooting
59

Publicidad

Capítulos

Tabla de contenido
loading

Este manual también es adecuado para:

Sunny tripower core1-us stp 33-us-41Sunny tripower core1-us stp 50-us-41Sunny tripower core1-us stp 62-us-41

Tabla de contenido