3. PREPARATION FOR SYSTEM INSTALLATION
3.2 INSTALLATION PLANNING
A little planning before beginning the installation can pay big dividends in reduced installation time and labor cost.
1. Review and measure the rack tier spacing to plan the routing of all cables.
2. It is recommended to mount the power supply after the DC splitter and manifold cables. This will enable you to determine the optimal
location to mount the power supply so all of the cables and power supply will reach each other when you're ready to plug them in.
3. When installing high vertical racks, connecting DC splitter cables to the fixtures during fixture assembly on the ground can reduce work
time required on the ladder or scissor lift.
SYSTEM COMPONENTS
Please refer to the RAZR Modular System Wiring Guide for details of
your ordered SKUs, including wiring diagrams, part list and accessories
to plan out the installation.
1.
48" LED Light Bar
3.
Power Supply
5.
DC Manifold Cable
Dust Cap
7.
Fixture Wire Hangers
2.
Light Fixture Frames
4.
DC Splitter Cable
6.
AC Power Cable
8.
DC Manifold Splitter Cable
(when using two DC manifold cables
per power supply)
3
2
1
4
7
5
8
6
9