Positioning
The MistEliminator can be mounted on the floor or on a
platform.
4.2
Tools and requirements
The following tools and requirements are needed to install the
system:
- lifting equipment
- level
- duct connection material
- wrenches
- electric drill + self-tapping screws (in case of optional outlet
unit for duct connection)
4.3
Unpacking
The MistEliminator filter banks are supplied in a pre assembled
way.
Check that the product is complete. The package should
contain:
Single base filter banks:
- assembled filter bank
- adjusting foot (4)
- oil container
Separately:
- ME-INLET/500: inlet connection Ø 500 mm, incl. mounting
material
- ME-INLET/COV: inlet cover plate Ø 500 mm, incl. mounting
material
Dual base filter banks:
- assembled filter bank (2) incl. outlet connections
- fixing plate
- adjusting foot (8)
- inlet joint kit, consisting of reinforcement ring (2), join ring,
sealing material (tube) and mounting material
- standard oil container (2)
Separately:
- ME-INLET/500: inlet connection Ø 500 mm (1 or 2), incl.
mounting material
- inlet cover plate Ø 500 mm (max. 1), incl. mounting material
If parts are missing or damaged, contact your supplier.
4.4
Installation
To mount the unit, proceed as follows.
WARNING!
Use sealed ductwork and duct connections to prevent
oil leakage.
Fig. 4.1
Mount 4 adjusting feet (A) underneath each filter bank.
0000101016/150119/C MistEliminator | Filter banks
A (x4)
Fig. 4.1: Adjusting feet
Single base filter banks (ME-XX/2 and ME-XX/3):
Place the unit at an appropriate position.
If necessary: use the adjusting feet to make it level.
Mount the inlet connection (ME-INL-500) on one side of the
air inlet module with the supplied mounting material.
Mount the inlet cover plate (ME-INL-COV) on the other side
of the air inlet module with the supplied mounting material.
Dual base filter banks (ME-XX/4 and ME-XX/5):
In case of ME-XX/5: start with the largest filter bank.
Place the first filter bank at an appropriate position.
If necessary: use the adjusting feet to make it level.
Fig. 4.2
Mount a reinforcement ring (A) at the inside of both filter
banks with the supplied mounting material.
A
Fig. 4.2: Reinforcement ring
Fig. 4.3
Apply sealing material to the outside of one/the largest filter
bank (A).
Fig. 4.3: Sealing material
Fig. 4.4
Place the join ring (A) on the sealing material with the
threaded bolts (B).
A