Decommissioning, dismantling, environmental protection
Personnel:
Protective equipment:
DANGER!
Risk of injury due to the disregard of the specified personal protective
equipment (PPE)!
For all disassembly work, please respect the use of the PSA which is specified
on the product data sheet.
Decommissioning
DANGER!
The procedures described here may only be carried out by skilled personnel as
described at the start of the chapter, this may only be done using PPE.
Requirements
The pump is disconnected from the chemical supply.
n
n
The pump is rinsed.
The decommissioning procedure is as follows:
1.
Before carrying out any work, first isolate the electrical supply completely and secure
it against being switched on again.
2.
Relieve pump internal pressure and line pressure.
3.
Drain the metering medium from the entire system without leaving any residue.
4.
Drain and remove operating and auxiliary materials.
5.
Remove the remaining processing materials and dispose of them in an
environmentally friendly way.
Dismantling
DANGER!
Risk of injury in case of improper dismantling.
Dismantling may be carried out only by skilled personnel using PPE.
Stored residual energy, components with sharp edges, points and corners, on
and in the system, or on the required tools can cause injuries.
Thoroughly rinse all components that come into contact with the product to
remove chemical residues.
Decommissioning, dismantling, environmental protection
n
Operator
n
Mechanic
n
Service personnel
n
Specialist
n
Protective gloves
n
Chemical-resistant protective gloves
n
Protective eyewear
n
Safety shoes
93