7- Flange
8- Injector (place with the arrow facing downwards)
9- Pipe nipple 3/8,1/2
10- Flange
11- Acid inlet (suction tube)
12- Acid outlet (injection tube)
13- pH probe connector (BNC)
14- pH4 calibration liquid
15- pH7 calibration liquid
16- Rubber cap for calibration
3.2.2.2- Connection of pH kit
Once the equipment (1) is installed, the following connections should be done.
1- Place the flange (10) in the pipe as indicated in the hydraulic connection
diagram. The flange (10) corresponds to the injector and should be connected
after the electrolysis cell.
2- Place the flange (7) in the pipe as indicated in the hydraulic connection
diagram. The flange (7) corresponds to the PH probe and should be
connected after the electrolysis cell and before the filter.
3- Connect one end of the suction tube (2) to the PH control inlet (11).
4- Connect the other end of the suction tube (2) to the suction filter (4).
58 / 95
Manual BSONE-EVO v.2