Descargar Imprimir esta página

Cupra CHARGER Manual De Instrucciones página 39

Publicidad

Idiomas disponibles

Idiomas disponibles

COMMISSIONING.
G ENE RAL COMM ISSI ONING.
Before connecting the wallbox to the vehicle:
1.
Clean the connection zone.
2.
Check wall mounting for stability.
3.
Check that all screws and terminal connections are tight.
4. Make sure there are no knock-out holes for cable routing left open.
Seal them with blind plugs if there is no cable routed through them.
5. Make sure all cable glands are tightly closed.
6. Perform visual inspection according to commissioning protocol.
7.
Switch on the input power to the wallbox.
8. Check HMI LED status indication.
9. Perform electric commissioning according to commissioning
protocol and normative requirements and additional local installation
requirements (if applicable).
10. Perform functional tests with a simulator or an EV and simultaneously
check HMI LED status indication.
11. Fill-in commissioning report.
If you need a commissioning report, find an example
of it at www.elli.eco/download.
MAINTENANCE.
The owner of the wallbox is responsible for the maintenance of the
charging station, whereby both the law regarding the safety of persons,
animals, and property must be observed, as well as the installation
regulations in force in the country of use.
1.
Dirt and natural organic matter on the outside of the charging
station can be cleaned off using a damp soft cloth.
2.
Check the charge plug for damage and for foreign matter.
Clean if necessary.
3.
Have the wallbox and its installation inspected by an electrician
on a regular basis and in compliance with your local country
installation guidelines.
4 0

Publicidad

loading