UNIT INSTALLATION
7.2 INSTALLATION PLACE PROVISION
•
Secure the outdoor unit with the anchor bolts.
Air Flow Direction
•
Fix the outdoor unit to the anchor bolts by field-supplied
special washer.
•
When installing the outdoor unit, fix the unit by anchor bolts.
Regarding the location of fixing holes
•
Example of fixing outdoor unit by anchor bolts.
A
Cut this portion when
this type of anchor
bolt is used. If not, it
is difficult to remove
the service cover
•
When installing the unit on a roof or a veranda, drain water
may turn to ice in a cold morning. Therefore, avoid draining in
an area where people often use because it is slippery.
In case of installing in such a place, provide the additional
drainage around the foundation.
Base
Nut
Special Washer(M10)
Rubber Mat
Anchor Bolt
(M8)
Concrete
(Unit: mm)
Concrete
Anchor bolt
Air Flow
Direction
•
The whole of the base of the outdoor unit should be
installed on a foundation. When using vibration-proof mat, it
should also be positioned in the same way. When installing
the outdoor unit on a field-supplied frame, use metal plates
to adjust the frame width for stable installation as shown in
figure.
Outdoor unit is
unstable
Frame
Outdoor unit
is stable
Frame
Recommended metal plate size (field-supplied
-
Material: Hot-rolled mild steel plate (SPHC)
Plate thickness: 4.5T
-
11
INCORRECT
60mm
Base width of
outdoor unit
<60mm
Frame width
(field supplied)
CORRECT
60mm
Base width of
outdoor unit
Metal plate
100mm or more
Metal plate