3.
INSTALLATION
THE BURNER MUST BE INSTALLED IN CONFORMITY WITH LEGISLATION AND LOCAL STANDARDS.
3.1
WORKING POSITION
The burner is designed to work only in the positions, 1 and 2.
Installation 1 is preferable, as it is the only one that allows performing maintenance operations as de-
scribed in this manual. Installations 2 allow working operations but not maintenance with hooking to the
boiler. Any other position could compromise the correct working of the appliance.
Installations 3, 4 and 5 are forbidden for safety reasons.
1
3.2
BOILER FIXING
To install the burner on the boiler, do the following:
Put on the flange (1) the screw and two nuts, (see fig. 3);
Widen, if necessary, the insulating gasket holes (5), (see fig. 4);
Fix the flange (1) to the boiler door (4) using screws (2) and (if necessary) the nuts (3) interposing the
insulating gasket (5), (see fig. 2).
After installation ensure that burner is lightly inclined as in fig. 5.
ATTENTION:
Boiler door must have a max. thickness of 180 mm, refractory linig included.
Fig. 2
Fig. 3
3402
2
3
4
4
S7144
GB
5
D7088
Fig. 4
D5012
Fig. 5
D5025