The inverters and the Inverter Manager must be
commissioned via the local commissioning and
service tool (LCS-Tool). Commissioning is required
before the inverters are connected to the utility grid
and start to feed-in power.
INFORMATION
The frmware update might cause
communication problems between Inverter
Manager and LCS-Tool.
• Perform the frmware update exactly as
described in this document(see
Section 5.2.5, page 32).
It is recommended to use the latest version of the
LCS-Tool:
•
rom frmware version 2.00.044 for PV
systems
•
rom frmware version 2.01.003 for
battery-storage systems
The hardware requirements for the LCS-Tool are:
• PC with Windows
• 1 GB HDD
• 2 GB RAM
igure 10: Commissioning inverters via the LCS-Tool
A
LCS-Tool
B
Router (DHCP recommended)
C
Inverter Manager
D
Sunny Tripower 60 /
Sunny Highpower 75
24
IMVIOBOX-IA-xx-18
TM
7 and later
SMA Solar Technology AG
The LCS-Tool must be installed on a local PC drive.
The PC must be connected to the LAN 1 port of the
Inverter Manager via a router (DHCP
recommended).
INFORMATION
The LAN 1 port of the Inverter Manager must
have an IP address assigned by a DHCP server
that is connected to the LAN 1 port. An IP address
can be manually assigned to the Inverter
Manager.
It is important that the computer (on which the
LCS-Tool runs) is connected to the same IP subnet
as the Inverter Manager.
The Inverter Manager may not be assigned an IP
from the system network range 192.168.4.0/24.
The LAN 1 port is reserved for the PC with the
LCS-Tool, for the router and for the power
analyzer. The LAN 2 port is intended for inverters
and battery-storage systems. The PC may be
connected to LAN port 2 with the LSC-Tool in
exceptional cases only (e.g. during servicing). To
do this, the DHCP protocol must be activated in
the communication settings of the PC.