Parflange 1050
5.4
Initial Operation
Before initial operation of the machine,
please check the level of the hydraulic
power unit and fill up the tank with
hydraulic oil (HLP 46), if required.
Before you connect the machine, make
sure that the main switch is set to „0-OFF".
Check the power supply to make sure that it
corresponds with the voltage of the
machine (type label / technical data).
Connect the 5-terminal 16A-CEE plug to
the power supply.
The fuse protection must not exceed 16A.
The standard delivery of the machine
includes a 5m long connection cable.
Switch the main switch "ON" and start the
machine with the ON
machine does not start, the emergency-off
key may be activated. By turning the
emergency-off switch to the right, it is
deactivated.
If the machine does not work, check the
turning direction and alter, if required.
Polarity correction:
Use a screw driver to give the compen-
sating poles of the mains plug a 180° twist.
In case of using a plug without polarity
switch device, a qualified electrian should
check the polarity and change it if required.
6.
6.1
The machine was designed and
constructed according to the acknowledged
KEY. If the
safety-technical rules and a careful
selection of the harmonising standards
which require observation. Therefore it is in
accordance with the present state of
technology and guarantees a maximum of
security.
This security, however, can only be
achieved in the working praxis, when the
accompanying measures have also been
taken. It belongs to the machine operator's
duty of care to plan these measures and to
make sure they have been carried out.
The operator must make particularly
sure that:
• the machine is used according to
• the machine is only operated in a
37
Attention!
Pull out the plug before
beginning to work!
Operation
Qualifications Required
directions only
flawless and well-functioning condition
and when all safety facilities in particular
are frequently checked on their
functioning order