16 TRANSPORT
Damaged or insufficiently strong hoists and load slings can result in serious injury or
even death. Before use, therefore, check hoists and load slings for adequate load-
bearing capacity and perfect condition. Secure the loads carefully. Never stand under
suspended loads!
To ensure proper transport, observe the instructions and information on the transport packaging
regarding centre of gravity, attachment points, weight, means of transport to be used and the
prescribed transport position, etc.
Transport the machine in its packaging to the place of installation. To manoeuvre the machine in
the packaging, a pallet truck or forklift truck with the appropriate lifting force can be used, for
example. Ensure that the selected lifting equipment (crane, forklift, pallet truck, load sling, etc.) is
in perfect condition. Lifting and transporting the machine may only be carried out by qualified
personnel with appropriate training for the lifting equipment used.
To position the machine at the installation location, proceed as follows:
When using a crane:
1.
Mount lifting eyes on the lifting points.
2.
Attach lifting slings.
3.
Lift the machine to its intended place, observing the balance.
The transport locks on the table and under the grinding wheel head may only be
removed after complete assembly.
17 ASSEMBLY
17.1
Preparatory activities
17.1.1
Checking delivery content
Always note visible transport damage on the delivery note and check the machine immediately
after unpacking for transport damage or missing or damaged parts. Report any damage to the
machine or missing parts immediately to your retailer or freight forwarder.
17.1.2
Cleaning and lubrication
Before you install and commission the machine at the intended location, carefully remove the
anti-corrosion protection and grease residues.
Under no circumstances should you use nitro thinner or other cleaning agents that could attack
the machine's paint.