MAINTENANCE INSTRUCTIONS
Regular monitoring of the machine is recommended. Before performing any maintenance, unplug the machine from
the mains and keep it unplugged during the maintenance operations. Reduce the recommended maintenance inter-
vals in situations of intensive use.
INTERVAL
Check the condition of wiring and external accessories
Replace worn components of the torch
Weekly
Clean and tighten the electrical connections of the welding circuit
Clean the wire feeder unit with compressed air
Blow the ventilation tunnel with compressed air (dry) from the front intake vents. Don't re-
move the vents during the operation
Quarterly
Remove all rollers from the drive unit (clean them to remove dust and dirt and then, lubri-
cate them slightly)
Annual
Carry out a complete inspection as specified by the standard EN-60974. See your dealer.
The handling of internal parts of the machine should be performed only by qualified personnel. There is a
risk of electric shock on contact with active parts. You should NOT operate without the covers properly
placed. Before accessing the interior of the machine, unplug it from the mains and wait at least 5 minutes
EXPLODED DRAWINGS
Aeropocess 2000
(A1)
Aerofeed 5
(A1)
Aeroprocess 3200
(A2)
Aeroprocess 3220
(A3)
SCHEMATICS
AEROPROCESS 3200
AEROPROCESS 3220
AEROPROCESS 2000
AEROFEED 5
SOLTER
SOLDADURA S.L.
ATTENTION
before carrying out any maintenance operation.
(A4)
(A5)
(A6)
(A7)
AEROPROCESS
ACTION
EN
21