4
Startup Operation
4.1
Preliminary checks prior to start-up
The following points must be checked before commissioning:
•
The auxiliary power must be switched off.
•
The auxiliary power must match the specifications started on the name plate.
Note
The connections for the auxiliary power can be found under the cover (1) in the connection
area.
Fig. 26
1 Cover
•
The pin assignment must correspond to the connection diagram.
•
The unit must be grounded properly.
•
The temperature limits must be observed.
•
The EEPROM (1) must be plugged on the display board in the transmitter. The EEPROM is
labeled with an order number and an end number. The end number can be found on the
name plate of the corresponding flowmeter primary. These numbers must be identical.
Fig. 27
1 EEPROM
D184B133U02
1
FXE4000 (COPA-XE/MAG-XE)
Startup Operation
G00147
EN - 23