3. PRE-OPERATION PROCEDURES
Installation Procedure
Be aware that slide panel may spring up
Slide panel on this unit employs a spring-loaded jack to lift it up.
The spring tension is adjusted to achieve balance when all the connection with glassware
and piping are made.
The panel jumps up when releasing the lock of the jack without glassware mounted.
Be sure to hold the top of the slide panel by hand whenever releasing the lock.
Always install glassware and piping with the slide panel lifted up.
If the lock of the jack is unintentionally released while setting up glassware and piping,
there is a risk of damage to glassware, and/or personal injury.
1. Jacking up
(1) Release the lock by turning jack handle
counterclockwise while holding the slide panel
top.
Hold the slide panel tightly or it may jump up.
LOCK
(2) Lift up the slide panel to top, turn the handle
clockwise to lock.
2. Motor box tilt adjustment
(1) Hold motor box by hand and turn tilt
adjustment screw counterclockwise to
release the lock.
(2) Motor box can now rotate. Rotate the box to
the position for use and turn tilt adjustment
screw clockwise to lock the driving unit.
(3) Adjust the control panel angle for better
visibility
Tilt the driving unit at about 30° before
installation.
FREE
Control panel
13
Slide panel
FREE
Jack handle
FREE
Motor box
Tilt adjustment screw
30°
Hold here by hand
LOCK