Installation

Fuel oil connection

Altitude correction
Suction (H+) or loading (H-) pump
Altitude (m)
Dummy H (m)
0-500
501-800
801-1300
1301-1800
1801-2200
e.g. Altitude 1,100m Dummy H=1m Real H=2m
Suction corrected H
2 + 1
= 3m
Load corrected H
2 - 1
= 1m
Choose pipe diameter in table, according to length
between tank and pump.
If suction corrected H exceeds 4m, have transfer pump
available (max. pressure 2 bars).
Double tube installation L (m)
Corrected
C 75 / C 100
H
Ø (mm)
(m)
10/12
12/14
4,0
51
83
3,0
45
83
2,0
38
82
1,0
32
69
+0,5
29
62
0
26
56
-0,5
22
49
-1,0
19
42
-2,0
13
29
-3,0
6
16
-4,0
0
2
Fuel oil connection
Enclosed diagrams provide required
pipe diameters.
There are two following possibilities:
Direct suction:
According to length L and suction or
load height H and chance mishaps;
These lengths include the presence
of a quarter-turn hand-operated
valve, a check valve and four
elbows.
Maximum negative pressure of
0.4bar.
Transfer loop:
According to the type of facility,
booster pump characteristics will
have to meet several criteria,
notably:
hourly flow,
fluid flow speed,
0
maximum boosting pressure.
0,5
Preference should be given to this
type of installation, in order to
1,0
obtain long spray pump life.
1,5
m
2,0
Important
In both cases, it is compulsory to
fit a 120µm² filter and quarter-turn
hand-operated valve on the suction
or booster (not supplied).
Important:
Suction:
· Totally fill suction pipe between
spray pump and tank down-pipe with
fuel oil.
Transfer loop:
14/16
· Fill, boost, drain and set pressure in
83
circuit at 2bar max. It is advisable to
83
install a pressure switch to limit
83
burner operation to boost pressure.
83
· Check for possible leaks.
83
83
83
80
55
31
6
06/2006 - Art. Nr. 13 013 497B
EN
31

Publicidad

Capítulos

Tabla de contenido
loading

Este manual también es adecuado para:

C 100

Tabla de contenido