en
5 Installation
Fig.194
1~1.5 m
Fig.195
5.8.4
Installing the cassette grid
Fig.196
2
5.9.1
Installation location
Fig.197 Floor installation
500
176
>1/100
MW-6020089-1
MW-6070068-01
1
500
MW-6070072-01
2. Ensure there is a downward gradient of 1/100-150.
3. Insulate the condensate pipe and drain tap (rubber insulation with a
thickness of more than 8 mm) to prevent condensation.
4. When draining multiple units into a shared condensate pipe, this
shared pipe should be installed about 100 mm below each unit's drain
tap, as shown in the drawing.
Important
During installation ensure that the wind guid in the grid (2)
corresponds to the position of the refrigerant pipe entry (1) into the
indoor unit.
The panel must be installed with the electrical connections facing
in the right direction. These must not be stretched or left hanging
inside the cassette. Make sure that the electrical cables are stored
in such a way that they do not interfere with the operation of the
appliance and do not damage it.
1. Attach the four clips on the grid to the hangers on the unit.
2. Fix the grid into position using the four bolts located inside the inlet
panel of the grid in the four corners.
When choosing the installation location, take into account the minimum
space requirements as described in the figures.
Select a suitable position in order to achieve a uniform air temperature
in the place of installation.
Make sure that the indoor unit is far enough from the food preparation
equipment to ensure that products are not attracted into the ceiling floor
unit
7800852 - v02 - 10052022