Instructions for installing the "CAF-
FETTERIA ITALIANA" model
CAUTION: RISK OF POLLUTION
Do not dispose of the packaging in the
environment. Before proceeding with all
installation and adjustment operations, the
qualified operator must be wearing work
gloves and protective footwear and must
have read and fully understood the safety
measures contained in the present book-
let.
After ensuring that the package contains
the accessories unit, place the machine
into its allotted setting and level it by regu-
lating the adjustable feet provided. Then
place the cleaning filter into its allotted
space. In all existing versions of the CAF-
FETTERIA ITALIANA model, the pump is
incorporated within the machine, thereby
simplifying attachment operations.
Before installing the machine's plumbing
unit, run water through the cleaning filter
to eliminate any impurities or grease resi-
dues.
At this point, a qualified operator can carry
out the definitive plumbing and electrical
instalments.
36
INSTALLATION AND ADJUSTMENTS
Should the amount of electric cable provi-
ded not be sufficient, always use cable of
the same width. Make sure that the elec-
tric system is provided an efficient groun-
ding system to attach to the appliance by
means of the yellow-green wire.
CAUTION: RISK OF SHORT CIR-
CUITS
We must remind the licensed electrician
that THE APPLIANCE MUST ALWAYS BE
PROTECTED BY AN AUTOMATIC SWIT-
CH OF SUITABLE POWER (220-
240V/12A).
The company cannot be held responsi-
ble for damage to things or injury to
persons caused by failure to comply
with the safety instructions and instal-
lation and maintenance instructions
contained in this handbook (and
reminds you that the said operations
must be carried out only by a qualified
operator).
To ensure that the appliance both lasts
and works well, installing a softener
and a filter not larger than 120 micron
onto the entrance tube is advisable.
Ensure that that there are at least 2
bars of pressure otherwise the hot
water mixer tap must be adjusted. To
reach the mixer, the right hand side of
the appliance must be removed.
Mixer tap Adjustment: during hot water
delivery phase handle the small knob
located just above the boiler; slightly
adjust the knob to modify the tempera-
ture of the water being delivered.
Moreover the pressure of the plumbing
system must not exceed 4 bar; otherwi-
se predispose a pressure reducer
ahead of the purifying filter.
CAUTION: RISK OF SHORT CIR-
CUITS
Before connecting the machine to the
electrical mains, check that the voltage it
has been predisposed for match (see,
technical features, pg. 10).
Connect the machine to the electrical
mains.
The machine is now in "stand by"; the "on"
button led will flash on and off.
SWITCHING ON THE APPLIANCE: to
switch on the machine, press the
on-off button; the appliance will enter its
self-diagnosis phase followed by a unit
positioning cycle and, if necessary, it will
proceed to filling up the coffee boiler and
the service boiler by means of the auto-
level.
NOTE: the appliance has a auto-level
maximum time of 60-90 seconds, after
which the function is arrested and the sign
SERVICE BOILER LEVEL ALARM will
appear. If this message appears during
the initial installation phase the machine
must be turned off (press the
on.off button for at least one second)
and then turned on again to finish filling up
;