7.4.3 CREATING VACUUM IN VACUUM CONTAINERS (CONTAINER OUTSIDE THE VACUUM CHAMBER)
1) Plug into a suitable electrical socket.
2) In case of first use, run the vacuum sensor calibration as described at § 6.1.
3) Place the container close to the packing machine on a flat, stable place.
4) Press PUMP key, then START to start the vacuum cycle.
5) Simultaneously press the two suction devices
ber
C
.
6) Once the required vacuum level (detectable through the vacuum
gauge) has been reached press STOP key.
7) Close the valve on the lid, in order to avoid any air return on the
container. Verify the cover seal.
After the cycle ending an acoustic signal advice that the machine is
ready for a new vacuum cycle.
Rev. 02 - 05/2016 - Cod. 1500015 - Instruction manual for vacuum chamber packaging machines EVOX 25 / EVOX 25 H
A
, on container lid
b
b
and on the suction point of vacuum cham-
C
C
OPERATION
A
29