Insert the lead and network data line through the
designated lead-throughs and fit the charging station
on the previously mounted bracket.
u
Mount the charging station using 2 screws, 6 x 90,
T25 through the mounting holes in the lower connec-
tion area.

Connecting the charging cable

u
Push the spiral antikink protection with the threadless
opening forward over the supplied charging cable.
u
Guide the charging cables through the previously pre-
assembled sealing clip.
NOTE
Ensure correct fit of the previously pre-assembled rubber
seals in the sealing clip.
u
Push the charging cable at least 1 cm beyond the up-
per edge of the clamping area of the strain relief
clamp.
u
Turn the antikink protection spiral several turns onto
the sealing clip.
NOTE
Do not tighten yet.
u
Screw in the supplied strain relief clamp in the correct
position on the charging cable.
NOTE
The strain relief clamp has two position options for char-
ging cable versions 11 kW and 22 kW.
Ensure that the "11 kW installed" label for a 11 kW char-
ging cable is not visible.
See also Fig. 6
Fit the strain relief clamp in the correct mounting pos-
u
ition using the supplied self-tapping Torx screws
(6.5 x 25 mm) and tighten to 5.5 Nm. (Attention: Do
not overtighten screws).
u
The strain relief clamp must be flush when securely
screwed in.
NOTE
Perform a tension test on the charging cable to make sure
that the cable cannot move.
u
Screw the antikink protection spiral onto the sealing
clip with a torque of 4 Nm.
5110326C_OI-II_Webasto Live Multilanguage
u
Using the slot-head screwdriver (3.5 mm), connect
the individual cable ends according to the specifica-
tion in the illustration on the right terminal block with
the "out" label.
u
To do this, insert the screwdriver in the designated
upper opening of the spring relief for the terminal
block and open the clamping spring.
u
Now insert the individual wire into the designated
connection opening of the terminal block (lower
opening).
Charging
Description
cable
N
Blue
Brown
L1
L2
Black
Grey
L3
Yellow-green PE
Black-white
Control cable (CP)
u
Then pull the screwdriver out again and perform a
tension test to make sure that the individual wires are
clamped properly and fully.
u
Connect the black/white control cable (CP) to the ter-
minal (contact A). See chapter 3.1.7, "Control cable
(Control Pilot)".
NOTE
Push the white spring contact of the connection on the
right down while inserting the control cable fully.
u
Perform a tension test to make sure that the cable is
clamped properly and fully.
6.4

The electrical connection

u
Check and make sure that the lead is tension-free and
measures have been taken to secure against being
switched on.
u
Check and comply with all the requirements neces-
sary for the connection and mentioned previously in
these instructions
u
Take the cable gland grommets from the supplied
material
u
Push the cable gland grommet over the lead (note:
Ensure that the insertion aid for the grommet is on
the back of the charging station when in the final in-
stalled state, however, do not position it in the hous-
ing lead-through yet)
u
If a data line is also to be connected, use the second
supplied cable gland grommet and repeat the above-
mentioned step.
NOTE
The bend radius of the data cable must be taken into ac-
count when connecting the data line. Use an angle plug
or adapter if necessary.
Remove the sheathing of the lead. See Fig. 4
u
If a rigid lead is used, bend the individual wires paying
u
attention to the minimum bend radiuses so that it is
possible to connect them to the terminals without
significant mechanical stress.
Remove the insulation from the individual wires as
u
per the illustration. (note: Avoid damage to the cop-
per braid)
u
Using the slot-head screwdriver (3.5 mm), connect
the individual cable ends according to the specifica-
tion in the illustration on the left terminal block with
the "Power In" label. (note: Make sure to connect
them using the correct connection sequence for a
right rotating field)
u
To do this, insert the screwdriver in the designated
upper opening of the spring relief for the terminal
block and open the clamping spring.
u
Now insert the individual wire into the designated
connection opening of the terminal block (lower
opening).
u
Then remove the screwdriver again and perform a
tension test to ensure that the individual wires are
clamped properly and fully and no exposed copper
areas are visible.