9. Carrying out trial run with / without material
It is recommended to first carry out a trial run without
material and drill bits to test all functions for proper
working order. If all functions are working properly, fit the
required tool.
Depending on connection, use the hand or foot switch for
function testing.
Start a trial run without material. Afterwards, you should
carry out a test with material.
Check work for correct results. You can start production if
all settings are correct.
Preliminary conditions
• All of the necessary activation processes must have been
carried out.
• The compressed air must be turned on.
• The machine must be set up for the relevant product.
• Make sure the machine is running smoothly and not
erratically.
• The operating personnel must always be informed about
current work procedure.
10. Concluding start-up
• After completing all servicing and set up work, make sure
everything has been done properly.
• Check all screws and connections for secure fit.
• After completing the check, you should carry out a test
using a component.
• Start up may only be concluded once the machine is
working properly.
• Now switch the machine off and hand over production to
the operating personnel.
• The operator must always be informed about the production
settings currently in effect and given instruction on work
procedure.
• Production can now commence.
NOTE
Following servicing work, check all safety guards for
proper working order.
en
121